OSU ackerman building

The Ohio State University

Project Specifics

Services Provided

  • BECx Services

Project Focus

  • BECx performance testing services

BECx Services

Technical Assurance was engaged by Heapy Engineering to provide BECx performance testing services during the renovation of the 700 Ackerman Building. The renovation space is a consolidated call center, and the renovated space will house offices for the Wexner Medical Center Central Scheduling & Customer Service, Health Plan, Corporate Operations, Hospital Compliance and OSU Physicians. The facilities had to remain operational with public access during construction.

Technical Assurance was engaged to provide performance testing. The challenge with the envelope construction of the project was specifically with the window and curtain wall installations, which tied into existing brick, and the brick did not have any weather barrier behind it. Performance tests included:

  • Aluminum Storefront Air and Water Leakage
  • Curtain Wall Air Leakage
  • Ribbon Windows Air Leakage
  • Air Barrier Transitions to Adjacent Systems
  • Curtain Wall Water Leakage
  • Window Water Leakage
  • Roofing Membrane Transitions Water Testing
  • Air Barrier to Transition Membrane Sealant Adhesion
  • Joint Sealants to Substrate Sealant Adhesion
  • Roofing Systems Electronic Leak Detection

Gallery

Have Peace of Mind with Technical Assurance

We are your expert partners in solving critical building envelope issues and extending the life of your facility’s assets. Request a consultation to get started!